This article provides a brief update on the key project
activities related to the Portland Harbor Superfund (PHSF) Site. The
PHSF Site is an 11.6-mile reach of the Lower Willamette River
between downtown Portland and the confluence with the Columbia
River. The remedial investigation of the site is getting close to
completion. After approximately 8 years, the draft remedial
investigation (RI) and baseline risk assessment (BLRA) reports are
expected to be submitted to the EPA before the end of 2009 and the
feasibility study (FS) is expected to be completed in 2010. Tens of
millions of dollars have been incurred to complete the field work
for the RI and BLRA. Additional costs will be incurred to prepare
the RI/BLRA report and FS. It was initially expected that a proposed
remedial plan and Record of Decision (ROD) would be issued in 2012,
but with the project’s history of delays due to the inherent
complexity of the Site, the ROD may be even further off.
In January 2008, USEPA issued CERCLA Section 104(e) information
request letters to about 280 current and former property owners,
tenants, or facility operators in the general vicinity of the Site.
Letters requested information about past material handling practices
and known or suspected releases of contamination to the Willamette
River. The USEPA will use this information to identify additional
PRPs prior to issuing the ROD for the Site. According to the USEPA,
a working group of PRPs are currently developing a process to
determine individual PRP’s allocation of liability and contribution
of investigation and remediation costs amenable to all. These costs
only include activities associated with the in-water investigation
and cleanup, and do not address costs associated with upland site
investigation, source control, or remediation activities. These
costs also do not include NRD costs. Reportedly, more than 120 PRPs
have agreed to participate in a voluntary, non-judicial settlement
process or signed tolling agreements with the respondents to the
Administrative Order on Consent (AOC) for the In-Water Work.
In April 2009, the original respondents to the AOC for in-water work
filed a lawsuit against 68 companies who had not previously agreed
to enter into the voluntary settlement allocation process noted
above, seeking payment for those companies’ share of the
investigation and remediation costs at the Site. The plaintiffs
estimate they have funded almost $70 million in investigation costs
for the Site since 2001. On June 23, the plaintiffs filed an amended
complaint reducing the number of defendants to 40.
As the date of the ROD draws near and with current estimates for
remediation ranging from $500 million to $1 billion liability,
allocation activities for the Portland Harbor RI/FS and remedial
action costs will likely accelerate in 2010.
For more information, please
contact John Elliott at (925) 403-6200.